New Web Banner Rev3 C96DPI

Relocated Wastewater Treatment Facility - Construction Updates

An overview of work completed and a projection of work expected in the following weeks is available here. The Contractor will notify property owners of any impact to their property or utility services. Please do not remove construction stakes or flags. Progress may differ from projections depending on the weather and other construction elements. See the November 26, 2025, construction update.

Previous work, December 11, 2023 - November 26, 2025:

  • Trees were removed along Lincoln Avenue, Smith Avenue, and Vireo Parkway.
  • Valley Corporation (Contractor) completed the force main installation along Vireo Parkway.
  • The Contractor completed the force main installation underneath US Highway 75 and along East Wiles Road both east and west of US Highway 75.
  • The Contractor completed the restoration of East Wiles Road, including seeding the ditches and placing new rock on the roadway east of US Highway 75.
  • The Contractor completed the force main installation along Chicago Avenue and 26th Avenue.
  • The Contractor completed the force main installation, utility installations, and the pavement restoration on Smith Avenue from 16th to Lincoln Avenues. Smith Avenue is open to traffic.
  • The Contractor completed the force main installation on Lincoln Avenue to Livingston Road and utility installations and main line pavement restoration on Lincoln Avenue to approximately Rhylander Park.
  • Livingston Road is open to traffic. Lincoln Avenue is accessible from Livingston Avenue for local traffic only.
  • The Contractor has completed the installation of new water main on 1st Avenue and Richey Street from 3rd to 2nd Avenues.
  • Lincoln Avenue from 6th Street to Livingston Road is closed to through traffic. Contractor will continue to provide access, where possible, to property owners in the road closure area while the pavement restoration is underway.
  • Contractor has completed installation of the sanitary sewer between 4th Street and Livingston Road, along with the installation of utilities on Richey Street.
  • Contractor has completed installation of the 12- and 24-inch force main pipelines.
  • Contractor started installation of the water main on South 5th Street from Lincoln to 4th Avenues.
  • Contractor completed pavement installation on Richey Street and 8th Avenue and installed sidewalk from 12th Avenue to Rhylander Park on Lincoln Avenue.
  • Contractor completed installation and tested the water main on South 5th Street from Lincoln to 4th Avenues.
  • Contractor completed pavement installation of the entrance to Rhylander Park near 6th Street.
  • Contractor completed pavement installation of the Lincoln Avenue and 6th Avenue intersection.
  • Contractor completed pavement installation on Lincoln Avenue from Livingston Road to 3rd Avenue.
  • Contractor completed pavement installation at the intersection of Livingston Road and 3rd Street.
  • Contractor continued with sidewalk and driveway pavement installations on Lincoln Avenue.
  • Contractor completed pavement installation along South 5th Street.
  • Contractor installed storm sewer inlets along Lincoln Avenue.
  • Contractor installed a retaining wall near the intersection of 5th Street and Lincoln Avenue.
  • Contractor installed a water main at the intersection of 4th Avenue and 4th Street and began preparations for pavement installation.
  • 3rd Avenue from Lincoln Avenue to 4th Street is closed to through traffic. Contractor will continue to provide access, where possible, to property owners in the road closure area while the pavement restoration is underway.
  • Contractor completed the pavement installation of the westbound lane of 3rd Avenue from Lincoln Avenue to 4th Street.
  • Contractor performed the pavement restoration to the damaged concrete panels along Lincoln Avenue.

Upcoming work overview, November 27 through December 10, 2025:

  • 3rd Avenue from Lincoln Avenue to 4th Street will remain closed to through traffic. Other areas may be reduced to one-lane traffic periodically during staging and construction activities.
  • Contractor will continue with the pavement installation along 3rd Avenue.

The Contractor’s schedule indicates that the completion of the project will take place in the next several weeks. Therefore, this will be the last construction update regarding the Wastewater Force Mains project. As the Contractor continues to finalize its work, items being completed or corrected will continue to be performed at various locations throughout the project area. If you have any questions, please contact Dan Martin with Strand Associates, Inc.® (Strand) at 402-319-4149 (mobile) or e-mail at This email address is being protected from spambots. You need JavaScript enabled to view it., or Steve Soupir with Strand at 515-233-0000 or e-mail at This email address is being protected from spambots. You need JavaScript enabled to view it..

Strand appreciates your patience and understanding during this important project for the City of Plattsmouth.

Construction Schedules

Contract 2 - February 28, 2025

Contract 3 - June 12, 2024

Contract 4 - March 26, 2025

Sanitary Sewer Improvements

sanitary sewer improvementsSanitary sewer improvements are part of the FEMA project to relocate the wastewate treatment plant as a result of the March 2019 flood. The project consists of the construction of a new wastewater treatment plant at the Fourmile Industrial Park, new pumping stations, and conveyance system. The sanitary sewer improvements will include removal and replacement of the existing surfacing on Smith Avenue, Lincoln Avenue, 2nd Avenue, and Richey Street. This will allow installation of sanitary sewer force mains, storm sewer installations, and water main relocations. Reconstruction will include new sidewalks and ADA accessible ramps.

The project is planned to be constructed in phases to minimize the disruption to residences and public access to Rhylander Park.

Project Information Sheet 

Strip Maps (recommend that you download the files and open them in Adobe Acrobat)

Strip map of Smith Avenue (from 16th Avenue south):

strip map S

Strip map of Lincoln Avenue (2nd to 12th Avenues) and Smith Avenue (12th to 16th Avenues):

strip map N

Wastewater Treatment Plant Groundbreaking

Over 50 people attended the groundbreaking for the new Wastewater Treatment Plant on March 3, 2023. Participating in the ceremony were Mayor Paul Lambert, City Administrator Emily Bausch, and former City Administrator/Assistant Director of Nebraska Emergency Management Agency Erv Portis along with City Council members and other dignitaries. See City Construction Projects for an update on the project's progress.

WWTP groundbreaking20230303